Supreme Court: Application for extension of the time period for passing an arbitral award - maintainable even after the expiry of the twelve-month or the extended six-month period.
Arbitration
Rohan Builders (India) Private Limited vs Berger Paints India Limited
September 12, 2024
Summary
Supreme Court has held that an application for extension of the time period for passing an Arbitral Award under Section 29A(4) read with Section 29A(5) of The Arbitration & Conciliation Act, 1996, is maintainable even after the expiry of the twelve-month or the extended six-month period, as the case may be. The while providing a guiding principle for courts stated that while adjudicating such extension applications courts have to be guided by the principle of sufficient cause and observations made in the judgment.